Production Team Dashboard v0.30 -
10:00
Pri | % complete | Project ID | Projects | Deadline | Countdown | Lead | Production | Material | Status | Startdate | Ganttlead |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 90% | 2025 A83.3 | GT11D5 U-Duct (21.05.) NEW | 28/07/2026 | 1 days | 👷 Marko Blažona | Dolenec | 100% | On-Time | 01/08/2025 | |
| 1 | 90% | 2025 A83.5 | GT11D5 HGC (16.6.) & CC-Tiles NW | 28/07/2026 | 1 days | 👷 Karlo Marciuš | Dolenec | 100% | On-Time | 20/08/2025 | |
| 1 | 60% | 2026 A87 | GT13E2 MXL consumables NMES PO8700002268 | 22/05/2026 | -66 days | 👷 Karlo Marciuš | Liptak | 80% | Delayed | 30/03/2026 | |
| 1 | 60% | 2026 A87.1 | GT13E2 MXL consumables NMES PO8700002342 | 19/06/2026 | -38 days | 👷 Karlo Marciuš | Liptak | 70% | Delayed | 13/04/2026 | |
| 2 | 20% | 2025 A73.4 | GT13E1 IL reco PO0863 Ind. P. | 15/08/2026 | 19 days | 👷Dušan Vrbanec | Ilija | 100% | On-Time | 16/10/2025 | |
| 3 | 40% | 2026 A77.10 | GT11N1 EGC HTS no.2 | 21/09/2026 | 56 days | 👷Daniel Preložnjak | Branko | 100% | On-Time | 17/03/2026 | |
| 1 | 80% | 2026 A6.10 | GT13E2 EGC 13E2 - RECO | 29/07/2026 | 2 days | 👷Daniel Preložnjak | Branko | 100% | On-Time | 19/03/2026 | |
| 3 | 70% | 2026 A77.11 | GT11N Shielding Cone PO2706 HTS | 12/8/2026 | 16 days | 👷 Karlo Marciuš | Matej | 100% | On-Time | 25/3/2026 | |
| 3 | 30% | 2026 A77.12-1 | GT11N1 HGC new PO2704 HTS | 25/09/2026 | 60 days | 👷 Karlo Marciuš | Dolenec | 70% | On-Time | 25/3/2026 | |
| 3 | 0% | 2026 A77.12-2 | GT11NM TVC new PO2704 HTS | 25/01/2027 | 182 days | 👷 Marko Blažona | Liptak | 0% | On-Time | 25/3/2026 | |
| 3 | 10% | 2026 A77.13 | HTS Belt Seal Segments PO 2716 | 01/12/2026 | 127 days | 👷Dušan Vrbanec | Liptak | 0% | On-Time | 01/04/2026 | 07/10/2026 |
| 3 | 10% | 2026 A77.14 | HTS Belt Seal Segments PO INP03312026 | 01/12/2026 | 127 days | 👷Dušan Vrbanec | Liptak | 0% | On-Time | 01/04/2026 | |
| 3 | 50% | 2026 A77.15 | GT11N2 Swirl Basket HTS PO04072026 | 26/08/2026 | 30 days | 👷Marko Blažona | 90% | On-Time | 10/04/2026 | ||
| 3 | 50% | 2026 A77.16 | HTS GT11NM Hardware PO04132026 | 04/08/2026 | 8 days | 👷Daniel Preložnjak | Liptak | 100% | On-Time | 14/04/2026 | 07/10/2026 |
| 3 | 5% | 2026 A89.1 | GT13DM HGC reco LBY 1st | 20/04/2027 | 267 days | 👷Dušan Vrbanec | 0% | On-Time | 16/04/2026 | ||
| 3 | 1% | 2026 A89.2 | GT13DM HGC reco LBY 2nd | 20/04/2027 | 267 days | 👷Dušan Vrbanec | 0% | On-Time | 16/04/2026 | ||
| 3 | 0% | 2026 A63.7 | PSC Marbach manpower | 31/07/2026 | 4 days | 👷Monico | 0% | On-Time | 16/05/2026 | ||
| 3 | 50% | 2026 A77.17 | HTS Swirler 2800/20 PO2744R1 | 22/09/2026 | 57 days | 👷Marko Blažona | 90% | On-Time | 22/04/2026 | ||
| 1 | 60% | 2026 A87.2 | GT13E2 MXL consumables NMES PO8700002437 | 30/06/2026 | -27 days | 👷 Karlo Marciuš | 50% | Delayed | 28/04/2026 | ||
| 3 | 5% | 2026 A77.18 | GT11N Ignition asy Nozzle line PO04292026 | 19/08/2026 | 23 days | 👷Marko Blažona | 95% | On-Time | 29/04/2026 | ||
| 3 | 40% | 2026 A77.19 | HTS GT11N LCCI parts | 06/10/2026 | 71 days | 👷 Lovro Nađ | 60% | On-Time | 06/05/2026 | ||
| 3 | 99% | 2026 A63.9 | PSC Sealing Ring PO6416 | 18/08/2026 | 22 days | 👷Dušan Vrbanec | 100% | On-Time | 03/06/2026 | ||
| 3 | 0% | 2026 A63.10 | PSC Air Mixing Nozzle PO6420 | 18/08/2026 | 22 days | 👷Dušan Vrbanec | 0% | On-Time | 04/06/2026 | ||
| 3 | 0% | 2026 A77.26 | HTS Exhaust Gas Casing GT11N1 PO06172026 | 20/12/2026 | 146 days | 👷Daniel Preložnjak | 0% | On-Time | 20/06/2026 | ||
| 3 | 10% | 2026 A77.25 | HTS Combustor Lower Cone PO06172026 | 20/09/2026 | 55 days | 👷 Karlo Marciuš | Dolenec | 90% | On-Time | 20/06/2026 | |
| 3 | 10% | 2026 A77.24 | HTS LCCI PO06172026 | 20/10/2026 | 85 days | 👷 Lovro Nađ | 70% | On-Time | 20/06/2026 | ||
| 3 | 0% | 2026 A77.23 | HTS CC-Tiles spring loaded PO06172026 | 20/06/2027 | 328 days | 👷Dušan Vrbanec | 0% | On-Time | 20/06/2026 | ||
| 3 | 0% | 2026 A77.22 | HTS Tile Carrier Row A-D PO06172026 | 20/09/2026 | 55 days | 👷 Lovro Nađ | 0% | On-Time | 20/06/2026 | ||
| 3 | 0% | 2026 A77.21 | HTS Turbine Vane Carrier PO06172026 | 20/06/2027 | 328 days | 👷Marko Blažona | 0% | On-Time | 20/06/2026 | ||
| 3 | 0% | 2026 A77.20 | HTS Hot Gas Casing PO06172026 | 20/12/2026 | 146 days | 👷 Karlo Marciuš | 25% | On-Time | 20/06/2026 | ||
| 3 | 0% | 2026 A87.3 | GT13E2 MXL consumables NMES PO8700002643, | 👷Antonio Hrastić | 100% | On-Time | 25/06/2026 | ||||
| 1 | 0% | 2026 A77.27 | HTS GT11N Segment Seals PO-INP7072026 | 15/09/2026 | 50 days | 👷 Marko Blažona | 0% | On-Time | 08/07/2026 | ||
| 2 | 0% | 2026 A77.28 | HTS GT11NM SHS/VANE assembly PO 2837 | 15/09/2026 | 50 days | 👷 Lovro Nađ | 95% | On-Time | 08/07/2026 |