Production Team Dashboard v0.30 -
10:00
Priority | % complete | Project ID | Projects | Deadline | Countdown | Lead 1 | Production | Status |
---|---|---|---|---|---|---|---|---|
1 | 80% | 2024 A81.5-KH3 | GT13D LCCI, Swirler NEW PO203-1632 | 15/11/2025 | 26 days | 👷 Marko Blažona | Peti | On-Time |
1 | 80% | 2024 A81.6-KH4 | GT13D LCCI, Swirler NEW PO203-1632 | 15/11/2025 | 26 days | 👷Marko Blažona | Peti | On-Time |
1 | 0% | 2024 A81.3-KH3 | GT13D HGC NEW PO599-1664 | 15/11/2025 | 26 days | 👷 Daniel Preložnjak | Ilija | On-Time |
1 | 0% | 2024 A81.4-KH4 | GT13D HGC NEW PO599-1664 | 15/11/2025 | 26 days | 👷 Daniel Preložnjak | Ilija | On-Time |
2 | 25% | 2024 A73.1-1st | GT13E1 HGC reco PO0616 Ind. P. | 1/10/2025 | -19 days | 👷Dušan Vrbanec | Liptak | Delayed |
2 | 10% | 2024 A73.1-1st | GT13E1 IL reco PO0616 Ind. P. | 1/10/2025 | -19 days | 👷Dušan Vrbanec | Liptak | Delayed |
3 | 10% | 2024 A73.1-2nd | GT13E1 HGC reco PO0616 Ind. P. | 1/1/2026 | 73 days | 👷Dušan Vrbanec | Liptak | On-Time |
3 | 10% | 2024 A73.1-2nd | GT13E1 IL reco PO0616 Ind. P. | 1/1/2026 | 73 days | 👷Dušan Vrbanec | Liptak | On-Time |
4 | 80% | 2024 A73.2 | GT13E1 HGC new PO0615 Ind. P. | 1/5/2026 | 193 days | 👷Dušan Vrbanec | Dolenec | On-Time |
5 | 0% | 🆕2025 A77.7 | GT11N L.Cone & Swirler NEW | 01/12/2025 | 42 days | 👷👷Karlo & Marko | Matej | On-Time |
6 | 0% | 🆕2025 A83.3 | 11D5 HGC (15.2.) & U-Duct (16.6.) NW | 15/02/2026 | 118 days | 👷👷Karlo & Marko | On-Time | |
7 | 0% | 🆕2025 A83.4 | 11D5 CC-Tiles NEW | 15/02/2026 | 118 days | 👷Dušan Vrbanec | On-Time | |
8 | 0% | 🆕2025 A83.5 | 11D5 LCCI (15.2.) & HGC (16.6.) & CC-Tiles NW | 16/06/2026 | 239 days | Karlo & Daniel | On-Time | |
9 | 0% | 🆕2025 A3.48 | LIB AFT END REPLACEMENT LTUS05581 | 15/10/2025 | -5 days | 👷Dušan Vrbanec | Delayed | |
10 | 0% | 🆕2025 A3.49 | LIB HGC 11N2 reco PARTS LTUS05687 | 01/02/2026 | 104 days | 👷Karlo Marciuš | On-Time | |
11 | 0% | 🆕2025 A3.50 | LIB HGC 11N2 reco PARTS LTUS05688 | 01/02/2026 | 104 days | 👷Karlo Marciuš | On-Time | |
12 | 0% | 🆕2025 A83.6 | GT11D5 DIFF FLANGE | 25/10/2025 | 5 days | 👷 Karlo Marciuš | Ilija | On-Time |
13 | 0% | 🆕2025 A77.8 | GT11N1 EGC NEW (penalties / late delivery) | 01/03/2026 | 132 days | 👷Daniel Preložnjak | Liptak | On-Time |
14 | 0% | 🆕2025 A3.51 | GT11N2 Split Line Ribs SET1 LTUS05768 | 05/12/2025 | 46 days | 👷Antonio Hrastić | On-Time | |
15 | 0% | 🆕2025 A3.52 | GT11N2 Split Line Ribs SET2 LTUS05769 | 05/12/2025 | 46 days | 👷Antonio Hrastić | On-Time | |
15 | 0% | 🆕2025 A63.5-B1 | GT13B PSC Inner Liner & U-Duct Collar | 30/01/2026 | 102 days | 👷Daniel Preložnjak | On-Time | |
15 | 0% | 🆕2025 A63.5-B2 | GT13B PSC Inner Liner & U-Duct Collar | 05/04/2026 | 167 days | 👷Daniel Preložnjak | On-Time | |
15 | 0% | 🆕2025 A63.5-B3 | GT13B PSC Inner Liner & U-Duct Collar | 05/04/2026 | 167 days | 👷Daniel Preložnjak | On-Time | |
15 | 0% | 🆕2025 A73.4 | GT13E1 IL reco PO0863 Ind. P. | 15/11/2026 | 391 days | Dodijeliti | On-Time |