Production Team Dashboard v0.30 -
10:00
Priority | % complete | Project ID | Projects | Deadline | Countdown | Lead | Material | Status | Startdate | Ganttlead | MASTER PLAN | GANT CHART | NACRTI |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 98% | 2026 A87.2 | GT13E2 MXL consumables NMES PO8700002437 | 30/06/2026 | -118 days | 👷 Karlo Marciuš | 100% | Delayed | 28/04/2026 | N/A | |||
| 1 | 80% | 2026 A77.12-1 | GT11N1 HGC new PO2704 HTS | 26/10/2026 | 0 days | 👷 Karlo Marciuš | 100% | On-Time | 25/3/2026 | ||||
| 1 | 0% | 2026 A77.34 | GT11NM Sealings PO 10162026 | 23/11/2026 | 28 days | 👷 Marko Blažona | 100% | On-Time | 16/10/2026 | ||||
| 1 | 70% | 2026 A77.24 | LCCI PO06172026 HTS | 20/10/2026 | -6 days | 👷 Marko Blažona | 100% | Delayed | 20/06/2026 | ||||
| 1 | 100% | 2026 A77.22 | Tile Carrier Row A-D PO06172026 | 10/10/2026 | -16 days | 👷Dušan Vrbanec | 100% | Delayed | 20/06/2026 | ||||
| 1 | 15% | 2026 A77.20 | Hot Gas Casing PO06172026 HTS | 20/12/2026 | 55 days | 👷 Karlo Marciuš | 85% | On-Time | 20/06/2026 | ||||
| 1 | 100% | 2026 A3.53 | HGC 11N2 Flow D parts - LTUS07122 | 16/10/2026 | -10 days | Nedodijeljeno | 100% | On-Time | 09/10/2026 | ||||
| 2 | 15% | 2026 A77.26 | Exhaust Gas Casing GT11NM PO06172026 HTS | 20/12/2026 | 55 days | 👷Daniel Preložnjak | 40% | On-Time | 20/06/2026 | ||||
| 2 | 80% | 2025 A73.4 | GT13E1 IL reco PO0863 Ind. P. | 15/11/2026 | 20 days | 👷Dušan Vrbanec | 100% | On-Time | 16/10/2025 | ||||
| 2 | 100% | 2026 A77.28 | GT11NM SHS/VANE assembly PO 2837 HTS (on track) | 15/11/2026 | 20 days | 👷 Marko Blažona | 80% | On-Time | 08/07/2026 | ||||
| 2 | 80% | 2026 A87.4 | GT13E2 MXL consumables NMES PO 8700002741 | 01/09/2026 | -55 days | 👷 Karlo Marciuš | On-Time | 20/07/2026 | |||||
| 2 | 80% | 2026 A87.5 | GT13E2 MXL consumables NMES PO 8300052006 | 01/09/2026 | -55 days | 👷 Karlo Marciuš | On-Time | 20/07/2026 | |||||
| 2 | 100% | 2026 A77.29 | Sealing Vane 2 PO2878 HTS | 11/10/2026 | -15 days | 👷 Marko Blažona | On-Time | 19/08/2026 | |||||
| 2 | 100% | 2026 A77.31 | Sealing Vane 2 INP08202026 HTS | 11/10/2026 | -15 days | 👷 Marko Blažona | On-Time | 19/08/2026 | |||||
| 2 | 0% | 2026 A77.33 | GT11N Parts HTP10017 HTS | 09/12/2026 | 44 days | 👷Daniel Preložnjak | On-Time | 09/09/2026 | |||||
| 3 | 65% | 2026 A77.10 | GT11N1 EGC HTS no.2 (on track) | 21/10/2026 | -5 days | 👷Daniel Preložnjak | 100% | Delayed | 17/03/2026 | ||||
| 3 | 20% | 2026 A77.12-2 | GT11NM TVC new PO2704 HTS | 25/01/2027 | 91 days | 👷 Marko Blažona | 30% | On-Time | 25/3/2026 | ||||
| 3 | 40% | 2026 A77.13 | Belt Seal Segments 4454 PO 2716 HTS | 01/12/2026 | 36 days | 👷Dušan Vrbanec | 40% | On-Time | 01/04/2026 | 07/10/2026 | |||
| 3 | 40% | 2026 A77.14 | Belt Seal Segments 4454 PO INP03312026 HTS | 01/12/2026 | 36 days | 👷Dušan Vrbanec | 40% | On-Time | 01/04/2026 | ||||
| 3 | 25% | 2026 A77.23 | CC-Tiles spring loaded PO06172026 HTS | 20/06/2027 | 237 days | 👷Dušan Vrbanec | 0% | On-Time | 20/06/2026 | ||||
| 3 | 20% | 2026 A77.21 | GT11NM Turbine Vane Carrier PO06172026 HTS | 20/06/2027 | 237 days | 👷Marko Blažona | 0% | On-Time | 20/06/2026 | ||||
| 3 | 100% | 2026 A87.3 | GT13E2 MXL NMES PO8700002643 - WAITING FOR PICKUP | 01/09/2026 | -55 days | 👷 Karlo Marciuš | 100% | On-Time | 25/06/2026 | ||||
| 3 | 20% | 2026 A63.14 | PSC GT13D Inner Liner NEW + Sealing Ring NEW + LCCI reco | 18/11/2026 | 23 days | 👷Antonio Hrastić | 100% | On-Time | 18/08/2026 | ||||
| 3 | 0% | 2026 A63.14_1 | PSC GT13D HGC Reco + BSS, Tension Spring, Terluran | 18/04/2027 | 174 days | 👷Dušan Vrbanec | On-Time | 18/08/2026 | |||||
| 3 | 0% | 2026 A77.32 | GT11NM EGH - PO HTP10009 HTS | 30/01/2027 | 96 days | 👷Daniel Preložnjak | On-Time | 09/09/2026 | |||||
| 3 | 0% | 2026 A41.4 | GT11D5 IL parts - PO #57002242 PMCO | 30/01/2027 | 96 days | 👷Antonio Hrastić | 0% | On-Time | 09/10/2026 | ||||
| 4 | 15% | 2026 A89.1 | GT13DM HGC reco LBY 1st | 22/12/2026 | 57 days | 👷Dušan Vrbanec | 0% | On-Time | 16/04/2026 | ||||
| 4 | 5% | 2026 A89.2 | GT13DM HGC reco LBY 2nd | 20/04/2027 | 176 days | 👷Dušan Vrbanec | 0% | On-Time | 16/04/2026 | 07/10/2026 |