Production Team Dashboard v0.30 -
10:00
Priority | % complete | Project ID | Projects | Deadline | Countdown | Lead 1 | Production | Status |
---|---|---|---|---|---|---|---|---|
1 | 90% | 2024 A81.5-KH1 | GT13D LCCI, Swirler NEW PO599-1664 | 01/06/2025 | -34 days | 👷Antonio Balent | Peti | Delayed |
1 | 80% | 2024 A81.6-KH2 | GT13D LCCI, Swirler NEW PO599-1664 | 01/06/2025 | -34 days | 👷Marko Blažona | Peti | Delayed |
2 | 40% | 2024 A80.1 | GT13D HGC NEW PO3332067 | 01/02/2025 | -154 days | 👷Daniel Preložnjak | Liptak | Delayed |
2 | 80% | 2022 A40.1-2SET | MHE Otočac hydro turbine - 2. SET | 18/6/2025 | -17 days | 👷 Karlo Marciuš | Matej | Delayed |
2 | 50% | 2022 A40.1-3SET | MHE Otočac hydro turbine - 3. SET | 29/7/2025 | 24 days | 👷 Karlo Marciuš | Matej | On-Time |
4 | 80% | 2024 A44.26 | GT13E2 EGC new PO | 1/6/2025 | -34 days | 👷Daniel Preložnjak | Liptak | Delayed |
4 | 50% | 2025 A3.47 | LIB 11N2 Annealing Fixture Reco LTUS05388 | 29/08/2025 | 55 days | 👷Antonio Hrastić | On-Time | |
6 | 0% | 2024 A81.5-KH3 | GT13D LCCI, Swirler NEW PO203-1632 | 01/06/2025 | -34 days | 👷Antonio Balent | Peti | Delayed |
7 | 0% | 2024 A81.6-KH4 | GT13D LCCI, Swirler NEW PO203-1632 | 01/06/2025 | -34 days | 👷Marko Blažona | Peti | Delayed |
8 | 0% | 2024 A81.3-KH3 | GT13D HGC NEW PO599-1664 | 01/08/2025 | 27 days | 👷 Daniel Preložnjak | Ilija | On-Time |
9 | 0% | 2024 A81.4-KH4 | GT13D HGC NEW PO599-1664 | 01/08/2025 | 27 days | 👷 Daniel Preložnjak | Ilija | On-Time |
9 | 20% | 2025 A83.2 | GT11D5 LCI exit collar NEW | 9/7/2025 | 4 days | 👷Antonio Hrastić | Ilija | On-Time |
10 | 25% | 2024 A73.1-1st | GT13E1 HGC reco PO0616 Ind. P. | 1/10/2025 | 88 days | 👷Dušan Vrbanec | Liptak | On-Time |
10 | 10% | 2024 A73.1-1st | GT13E1 IL reco PO0616 Ind. P. | 1/10/2025 | 88 days | 👷Dušan Vrbanec | Liptak | On-Time |
11 | 10% | 2024 A73.1-2nd | GT13E1 HGC reco PO0616 Ind. P. | 1/1/2026 | 180 days | 👷Dušan Vrbanec | Liptak | On-Time |
11 | 10% | 2024 A73.1-2nd | GT13E1 IL reco PO0616 Ind. P. | 1/1/2026 | 180 days | 👷Dušan Vrbanec | Liptak | On-Time |
12 | 80% | 2024 A73.2 | GT13E1 HGC new PO0615 Ind. P. | 1/5/2026 | 300 days | 👷Dušan Vrbanec | Dolenec | On-Time |
16 | 98% | 2023 A77.3 | ASSEMBLY GT13DM consumables | 15/7/2024 | -355 days | 👷 Daniel Preložnjak | Hrastić | Delayed |
17 | 0% | 2025 A86 | GT13E2 ASSEMBLY PARTS | 30/6/2025 | -5 days | 👷Antonio Hrastić | Hrastić | Delayed |
17 | 0% | 🆕2025 A77.7 | GT11N L.Cone & Swirler NEW | 01/12/2025 | 149 days | 👷👷Karlo & Marko | Matej | On-Time |
17 | 0% | 🆕2025 A83.3 | GT11D5 HGC & U-Duct NEW | 15/02/2026 | 225 days | 👷👷Daniel & Marko | On-Time | |
17 | 0% | 🆕2025 A83.4 | GT11D5 CC-Tiles NEW | 15/02/2026 | 225 days | 👷Antonio Balent | On-Time | |
18 | 0% | 🆕2025 A83.5 | GT11D5 HGC & LCCI & CC-Tiles NEW | 16/06/2026 | 346 days | 👷👷Daniel & Balent |