Priority | % complete | Project ID | Projects | Deadline | Countdown | Lead | Material | Status | Startdate | Ganttlead | MASTER PLAN | GANT CHART | NACRTI | DIMENZIJSKI PROTOKOLI |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 100% | 2026 A87 | GT13E2 MXL consumables NMES PO8700002268 | 22/05/2026 | -126 days | 👷 Karlo Marciuš | 100% | Delayed | 30/03/2026 | N/A | ||||
| 1 | 100% | 2026 A87.1 | GT13E2 MXL consumables NMES PO8700002342 | 19/06/2026 | -98 days | 👷 Karlo Marciuš | 100% | Delayed | 13/04/2026 | N/A | ||||
| 1 | 98% | 2026 A87.2 | GT13E2 MXL consumables NMES PO8700002437 | 30/06/2026 | -87 days | 👷 Karlo Marciuš | 100% | Delayed | 28/04/2026 | N/A | ||||
| 1 | 70% | 2026 A77.12-1 | GT11N1 HGC new PO2704 HTS (25.10. check if okay) | 25/09/2026 | 0 days | 👷 Karlo Marciuš | 100% | On-Time | 25/3/2026 | |||||
| 2 | 15% | 2026 A77.26 | HTS Exhaust Gas Casing GT11N1 PO06172026 | 20/12/2026 | 86 days | 👷Daniel Preložnjak | 40% | On-Time | 20/06/2026 | |||||
| 1 | 90% | 2026 A77.25 | HTS Combustor Lower Cone PO06172026 (15.10. ready) | 20/09/2026 | -5 days | 👷 Karlo Marciuš | 100% | Delayed | 20/06/2026 | |||||
| 1 | 70% | 2026 A77.24 | HTS LCCI PO06172026 | 20/10/2026 | 25 days | 👷 Marko Blažona | 100% | On-Time | 20/06/2026 | |||||
| 1 | 80% | 2026 A77.22 | HTS Tile Carrier Row A-D PO06172026 (ringovi?) | 20/09/2026 | -5 days | 👷Dušan Vrbanec | 100% | Delayed | 20/06/2026 | |||||
| 1 | 70% | 2025 A83.5 | CC-Tiles | 28/07/2026 | -59 days | 👷Dušan Vrbanec | ||||||||
| 2 | 80% | 2025 A73.4 | GT13E1 IL reco PO0863 Ind. P. | 15/11/2026 | 51 days | 👷Dušan Vrbanec | 100% | On-Time | 16/10/2025 | |||||
| 2 | 60% | 2026 A77.28 | HTS GT11NM SHS/VANE assembly PO 2837 (on track) | 15/11/2026 | 51 days | 👷 Lovro Nađ | 80% | On-Time | 08/07/2026 | |||||
| 2 | 80% | 2026 A63.15 | PSC Installation Hardware | 01/10/2026 | 6 days | 👷Daniel Preložnjak | On-Time | 11/08/2026 | ||||||
| 2 | 80% | 2026 A87.4 | GT13E2 MXL consumables NMES PO 8700002741 | 01/09/2026 | -24 days | 👷 Karlo Marciuš | On-Time | 20/07/2026 | ||||||
| 2 | 80% | 2026 A87.5 | GT13E2 MXL consumables NMES PO 8300052006 | 01/09/2026 | -24 days | 👷 Karlo Marciuš | On-Time | 20/07/2026 | ||||||
| 2 | 0% | 2026 A77.29 | HTS Sealing Vane 2 PO2878 | 11/10/2026 | 16 days | 👷 Lovro Nađ | On-Time | 19/08/2026 | ||||||
| 2 | 0% | 2026 A77.31 | HTS Sealing Vane 2 INP08202026 | 11/10/2026 | 16 days | 👷 Lovro Nađ | On-Time | 19/08/2026 | ||||||
| 2 | 0% | 2026 A77.33 | HTS GT11N Parts HTP10017 | 09/12/2026 | 75 days | 👷Daniel Preložnjak | On-Time | 09/09/2026 | ||||||
| 3 | 65% | 2026 A77.10 | GT11N1 EGC HTS no.2 (on track) | 21/10/2026 | 26 days | 👷Daniel Preložnjak | 100% | On-Time | 17/03/2026 | |||||
| 3 | 20% | 2026 A77.12-2 | GT11NM TVC new PO2704 HTS | 25/01/2027 | 122 days | 👷 Marko Blažona | 30% | On-Time | 25/3/2026 | |||||
| 3 | 40% | 2026 A77.13 | HTS Belt Seal Segments PO 2716 | 01/12/2026 | 67 days | 👷Dušan Vrbanec | 40% | On-Time | 01/04/2026 | 07/10/2026 | ||||
| 3 | 40% | 2026 A77.14 | HTS Belt Seal Segments PO INP03312026 | 01/12/2026 | 67 days | 👷Dušan Vrbanec | 40% | On-Time | 01/04/2026 | |||||
| 3 | 90% | 2026 A77.15 | GT11N2 Swirl Basket HTS PO04072026 (7.9. ready) | 26/08/2026 | -30 days | 👷Marko Blažona | 100% | Delayed | 10/04/2026 | |||||
| 3 | 85% | 2026 A77.16 | HTS GT11NM Hardware PO04132026 (6.9. ready) | 04/08/2026 | -52 days | 👷 Lovro Nađ | 100% | Delayed | 14/04/2026 | 07/10/2026 | ||||
| 3 | 5% | 2026 A89.1 | GT13DM HGC reco LBY 1st | 15/12/2026 | 81 days | 👷Dušan Vrbanec | 0% | On-Time | 16/04/2026 | |||||
| 3 | 5% | 2026 A89.2 | GT13DM HGC reco LBY 2nd | 20/04/2027 | 207 days | 👷Dušan Vrbanec | 0% | On-Time | 16/04/2026 | |||||
| 2 | 80% | 2026 A77.19 | HTS GT11N LCCI parts (on track) | 06/10/2026 | 11 days | 👷 Marko Blažona | 80% | On-Time | 06/05/2026 | |||||
| 3 | 25% | 2026 A77.23 | HTS CC-Tiles spring loaded PO06172026 | 20/06/2027 | 268 days | 👷Dušan Vrbanec | 0% | On-Time | 20/06/2026 | |||||
| 3 | 0% | 2026 A77.21 | HTS Turbine Vane Carrier PO06172026 | 20/06/2027 | 268 days | 👷Marko Blažona | 0% | On-Time | 20/06/2026 | |||||
| 1 | 15% | 2026 A77.20 | HTS Hot Gas Casing PO06172026 | 20/12/2026 | 86 days | 👷 Karlo Marciuš | 85% | On-Time | 20/06/2026 | |||||
| 3 | 100% | 2026 A87.3 | GT13E2 MXL consumables NMES PO8700002643, | 01/09/2026 | -24 days | 👷 Karlo Marciuš | 100% | On-Time | 25/06/2026 | |||||
| 3 | 20% | 2026 A63.14 | PSC GT13D Inner Liner NEW + Sealing Ring NEW + LCCI reco | 18/11/2026 | 54 days | 👷 Karlo Marciuš | 100% | On-Time | 18/08/2026 | |||||
| 3 | 0% | 2026 A63.14_1 | PSC GT13D HGC Reco + BSS, Tension Spring, Terluran | 18/04/2027 | 205 days | 👷Dušan Vrbanec | On-Time | 18/08/2026 |